In a striking blow, stripping a city of a judgment of nearly $1 million, the Massachusetts Appeals Court recently reversed a superior court summary judgment awarding fines to the City of Haverhill for a developer’s violations of zoning laws. The city assessed the fines against the developer under the state building code and the local zoning bylaw for building without necessary permits. In Maroney v. Planning Board of Haverhill, the Appeals Court held that the city’s building inspector did not follow the required procedures to impose fines.

The developer, Maroney, had a special permit and subdivision plan approval for a 50‑lot residential subdivision, both of which required him to build a water pressure booster station to service certain lots in the subdivision. The developer built much of the subdivision, in conformance with the process outlined by the city, on lots that the water department considered serviceable. When Maroney attempted to go forward with development of lots that the water department considered

Breaking: City of Boston Announces New Protocol for Resumption of “Essential” Construction This Month

Practice area:
Industries:

Late yesterday Boston Mayor Marty Walsh’s office announced a new protocol for re-starting city construction projects deemed “essential.” In mid-March, in response to the COVID-19 pandemic, Walsh ordered most construction in the city to cease. Since April 27, 2020, all projects involving essential construction have been required to file with the city a COVID-19 Safety Plan and an affidavit pledging to implement that plan. Starting yesterday, projects with approved safety plans and signed affidavits were allowed to begin preparing their construction sites with project-specific COVID-19 safety measures.

Under the new protocol, starting May 18, 2020, projects that (1) have all necessary permits in place, (2) have approved safety plans and signed affidavits on file, and (3) are sufficiently prepared to implement their safety plans, can resume construction, but only if the work is for:

  • hospitals;
  • public schools;
  • residential buildings of 1-3 units;
  • road and utility work; or
  • “other outdoor/open-air work such as steel